Smithfield North Booster Pump Station Upgrade

UPDATED: December 11, 2025

  • Contractor: Locke-Lane Construction, Inc.
  • Construction Contract: $1,118,811
  • Project Completed On: January 17, 2025
  • Description: This project involved the demolition and removal of the existing booster pump station, generator, and associated electrical equipment. It included the construction and installation of a new 1.5 MGD pre-packaged duplex booster pump station, a new generator, site improvements, yard piping, structural works (including new slabs for the pump station and generator), and electrical and SCADA upgrades. The project also covered erosion control, testing, and site restoration. The work was located at the existing Smithfield North Booster Pump Station Site at 3145 Buffalo Road in Smithfield.