210 WWTF

210 WWTF

UPDATED: December 18, 2025

  • Contractor: Adams Robinson, Inc.
  • Construction Contract: $68,754,000
  • Project Completed On: November 6, 2024
  • Description: This project involved the construction of several new facilities, allowing the treatment of 4 MGD of wastewater. The new facilities included a preliminary treatment facility, an effluent distribution box, BNR basins with fine bubble diffusers, mixers, and pumps, a blower building, secondary clarifiers, a recycled activated sludge pump station, chemical storage and feed facilities, a drain pump station, and disk filters. Additionally, the project will include a new sodium hypochlorite facility, an effluent pump station, a cascade aerator, and new maintenance and administration buildings.
  • Map


Pipe Icon
CONTACT

Johnston County Public Utilities Engineering Department

919-209-8333