CJCRWWTF PTF Improvements

UPDATED: July 29, 2025

Project Start Date: 1-30-2023

Estimated Completion Date: 8-12-2024 

The Work is located in Smithfield, NC at the Central Regional Wastewater Treatment Facility
(CRWWTF) site located at 1000 E. Huntly Street, Smithfield NC 27577. The Work consists of
the following:


1. Replacement of fine screens in an existing structure, new screenings conveyor,
new screenings compactor, and replacement of existing slide gates in the
screenings wetwell.
2. New grit removal facility with classifier.
3. Relocation of electrical and process piping in the vicinity of the new grit removal
facility.

 