  • Contractor: Ralph Hodge Construction Co.
  • Construction Contract: $825,906
  • Project Completed On: June 12, 2024
  • Description: This project involved installing approximately 4,272 linear feet of 8-inch force main from the Holt Lake Sewer Pump Station to an existing 12-inch gravity sewer line. The project also included upgrading the Holt Lake Wastewater Pump Station to a capacity of 700 GPM, which involved a new generator pad and retrofitting the existing wet well.