Central Regional WWTF SCADA Improvements
UPDATED: July 29, 2025
Project Start Date: 1-13-2025
Estimated Completion Date: 7-14-2026
The Work is located in Smithfield, NC at the Central Regional Wastewater Treatment Facility (CRWWTF) site located at 1000 E. Huntly Street, Smithfield NC 27577. The Work consists of the following:
1. Replacement of fine screens in an existing structure, new screenings conveyor, new screenings compactor, and replacement of existing slide gates in the screenings wetwell.
2. New grit removal facility with classifier.
3. Relocation of electrical and process piping in the vicinity of the new grit removal facility.